Beckwithshaw Cricket Club, Harrogate - 9 -10 October 2010
This was the first course to be held at Beckwithshaw Cricket Club. The weather was very kind with the Sunday being more like a summers day. The students worked on two sections of wall including building 2 new wall ends and produced a great job for first time wallers
Photos: Roger Johnson
Day 1 - stripped and ready to build
Foundations starting to go in
Keith must have dropped a penny. All stop till it's found!
Well on with the build now
The stone is running out now
Cock & Hen top stones placed
New gap constructed to stop the cricketers climbing the wall
Day 2 - Stripped out again
Bags of rubble brought in to ensure enough packings
Dealing with the tree roots
Still digging
Nice clean trench ready to build
There's always one isn't there!
Build finished and only just enough stone
Tidy job and a tidy site (except for someone hanging their washing out)
Great job by the students walling for the first time